City of Airdrie roadwork's - 2006 and 2007, works included subgrade, base,
paving, concrete and underground.
City of Medicine Hat various subdivision development including underground,
roadworks and concrete. (underground and concrete work subcontracted out).
Airdrie Walmart parking lot. Various town project.
Drumheller
Black Diamond
Okotoks
Redcliff
Crossfield
Highways
Deerfoot Trail extension from Hwy 22X to Hwy 2. Large $25,000,000 plus project
with approx. 800,000 tonnes of GBC and 200,000 tonnes of asphalt mix.
Aldersyde interchange on Highway 2 south of Calgary.
Various asphalt overlays, recently Highway 1 near Redcliff, 105,000 tonnes.
Current Projects
Northwest Calgary ringroad - Stoney Trail, largest non P3 Alberta
Transportation project to date $90+ million, over 900,000 tonnes of base and
270,000 tonnes of asphalt.
Balzac mega mall roads and parking lots in excess of 30 million.
Highway 2 near Crossfield, widening the median and adding lanes, 200,000
tonnes of base and 200,000 tonnes of asphalt.
Asphalt overlays on Glenmore Trail east of Calgary, Highway 2 near Cayley,
Secondary Highways 529, 533, 564, ...